Combining demand time series and demand segment
The distribution of travel demand is coded in standard time series and trip demand is coded in matrices. To combine both data, you need to allocate each standard time series to a demand time series first (Creating demand time series). Furthermore, each demand matrix needs to be combined with a demand segment (Connecting demand matrices and demand segments). Then each demand time series needs to be combined with the corresponding demand segment.
1. On the Demand menu, click Demand data.
The Demand data window opens.
2. Select the Demand segments tab.
3. In the list, select the demand segment you would like to combine with a demand time series.
4. In the Demand time series selection list, click the desired demand time series.
The demand time series is connected to the demand segment.