Exporting subnetworks via ANM interface

Using the subnetwork generator, you can generate a subnetwork and import it into Vissim via the ANM interface. For the subnetwork, you can then carry out the procedure sequence of the version opened again.

1.  From the Calculate menu, choose ANM export of a subnetwork.

The ANM export subnetwork window opens.

2.  Make the desired changes.

Element

Description

Subnetwork generator

Use parameter file

Select this option to enter the path and name of the subnetwork parameter file *.xml, or click the icon to select a file.

Specify parameters for subnetwork generator

Select this option to click to the Subnetwork generator button and specify the settings for the subnetwork generator (Subnetwork generation)

Procedure sequence section

Procedure sequence

no procedure sequence

If this option is selected, no procedure sequence is carried out for the subnetwork.

only PrT assignments as in version opened

If this option is selected, the same PrT assignments are carried out as in the opened version.

Note

The program performs an assignment for each PrT demand segment with a demand matrix exported into a subnetwork. The settings last calculated in the opened version are adopted.

as in open version

If this option is selected, only the active procedures of the opened version are carried out.

Note

The program only accounts for PrT demand segments with a demand matrix that were exported into a subnetwork. The settings last calculated in the opened version are adopted.

From file

Select this option to enter the path and name of a procedure parameter file *.par or *.xml, or to select a file via the symbol (Reading procedure parameter settings from file).

ANM export

 

Use parameter file

Select this option to enter the path and name of the ANM export parameter file *.anmp, or click the icon to select a file.

Specify parameters for ANM export

Select this option to click the ANM export parameters button to specify the settings for the ANM export (Saving an abstract network model).

Importing files into PTV Vissim

If this option is selected, the subnetwork is automatically opened in a new instance of PTV Vissim.

Note

Routes are imported as static routes into Vissim. Do not select this option if you want to carry out dynamic assignment in Vissim. In this case, you need to import the subnetwork manually via the ANM interface into Vissim.

3.  Confirm with OK.

The ANM export subnetwork is created.