Selecting a calendar

With the aid of the calendar, you can model the transport supply and demand in much greater detail. You can not only model any day, but also any combinations of weekdays or single days.

Note: Use of the calendar is optional.

Valid days are closely linked to the calendar (Creating a valid day)as they can be specified for the corresponding calendar

The calendar has an effect on the dynamic assignment (PrT) and the PuT analysis, (Using the graphical and tabular timetable) as valid days can be allocated to individual vehicle journeys in the timetables.

1.  On the Network menu, click Network settings.

The Network settings window opens.

2.  Select the Calendar and analysis period tab.

3.  In the Calendar section, select one of the following options:

Element

Description

No calendar

PuT supply and demand are modeled for an unspecified recurring day. A standard given valid day (daily) is used for this purpose.

Weekly calendar

PuT supply and demand are modeled separately for the individual weekdays Monday - Sunday.

Annual calendar

PuT supply and demand are modeled for any time period within the calendar period.

Calendar start, calendar end

Via the button you can open a calendar and select the beginning or the end of the calendar period with a mouse click on the desired date.

Tip

Alternatively, you can enter the desired start date and end date in the entry fields.

Notes: For each network or version file, only one calendar option can be selected.

If the calendar settings are changed, all previously created valid days, blocks and PuT analyses will be deleted.

4.  Confirm with OK.

The settings are applied.